Risk register

What could move a deadline, how we would know, and what we do about it

Ten risks, scored likelihood times impact on a three-point scale. Each one names the trigger that tells us it is happening and the response that is already in the activity list. The register lives in data/risks.csv; close a risk by setting its status, and add one when a sync surfaces a new way to lose a deadline.

The matrix

Low impact
Medium impact
High impact
High likelihood
0
2R02, R07
1R01
Medium likelihood
1R10
3R05, R09, R11
4R03, R04, R06, R08
Low likelihood
0
0
0

The register

ID Phase Risk Likelihood Impact Score Trigger Response Owner Activities Status
R01 Proposal Fifth member is not on the official repo and the course guideline says teams of three to four; a five-name proposal submitted from a repo he cannot access raises questions High High 9 Still missing from the official repo on Sep 18 Ask the professor at the workshop meeting to add him and to confirm the team size Team S05 Open
R02 Proposal Draft carries AI paste artifacts and no references; the professor spots them at once and the Organization and Writing points go High Medium 6 Artifact string or chatgpt link still in the .qmd at render Blocking-fix list in the Sep 16 review; a second reader checks the rendered HTML before the push Team P06, P07 Open
R03 Proposal The professor challenges the topic on the emerging and pre-commercial criteria (smart locks and thermostats are common in new Class A buildings) and asks the team to narrow scope Medium High 6 Pushback at the workshop meeting Lead with the design-decision argument: which features to bundle at what premium for mid-market and retrofit stock; no public tradeoff-based WTP exists; be ready to drop lighting or EV charging Team P05, P06 Open
R04 Survey plan Price attribute mis-specified: a zero-dollar premium makes a free smart package a valid profile and there is no base-rent anchor, so the WTP estimates are biased Medium High 6 Design file generated with the draft levels Fix in SP01: reserve zero for the standard-apartment reference or shift the range; show a base rent in every choice task Team SP01, SP03 Open
R06 Pilot survey Survey hosting breaks: Supabase not connected, shinyapps deploy fails, or a key leaks into the repo Medium High 6 Responses not stored in a test run; a key in a diff Assign the account owner by Oct 2 (S07); keys in .Renviron only; end-to-end test on Oct 12 at the latest Account owner S07, PS04, PS05 Open
R07 Final survey Weeks 9 to 13 stack HW8 to HW12, three quizzes and three deliverables; the pilot-to-final handoff has one day of float High Medium 6 Any pilot-analysis activity slips past its planned finish Start cleaning on partial pilot data (PA02); triage feedback in parallel (PA05); owners agree a weekly time budget before Oct 21 Team PA02, PA05, FS01 Open
R08 Final analysis Prolific fielding starts late or runs long over Thanksgiving, leaving days rather than weeks between the final data and the Dec 6 report, with the Dec 2 exam in between Medium High 6 Launch not confirmed by Nov 11; fewer than the target responses by Nov 25 Confirm the launch date at the Nov 11 class; scaffold every script on the pilot data (FA01) so the final run is a re-run Team FS04, FA01, FA02 Open
R05 Pilot analysis Six attributes at three to four levels each overloads respondents and the pilot standard errors are too wide to size the final sample Medium Medium 4 Pilot coefficient standard errors dwarf the estimates Pilot with the full set; drop or merge the weakest attribute (lighting is the likely candidate) in FS01 Team PA03, PA04, FS01 Open
R09 Ongoing Uneven contribution; the professor grades non-contributors differently and the Attribution section has to be honest Medium Medium 4 CONTRIBUTIONS.md shows one or two names for a deliverable Owner and backup per deliverable (S06); contributions logged weekly (O03); raise it at the sync, not at submission Team S06, O03 Open
R11 Survey plan The survey plan repeats the proposal's GWU-network distribution while the course expects Prolific with an eligibility pre-screen; the final survey then lacks a fielding plan the professor can run Medium Medium 4 SP02 drafted without naming Prolific and the exact eligibility text Decision D07: state Prolific as the strategy for the final survey, classmates for the pilot, networks as a supplement; write the eligibility question text in the plan Team SP02, FS03 Open
R10 Ongoing Decisions made on WhatsApp never reach the repo and the team re-argues them Medium Low 2 A decision cannot be found in decisions/DECISIONS.md Same-day copy rule (O01); the tracker maintainer checks the log at each sync Harshit O01 Open

EMSE 6035 team project tracker. Public site: no grades, no personal details, no credentials.

 