Team Project Tracker

EMSE 6035 · Marketing Analytics for Design Decisions · GWU · Fall 2026 · Team E · Smart Urban Living

One page that knows where the team project stands. The schedule below is not typed in: every render runs a critical path method over data/activities.csv (early and late dates, total float, the zero-float chain) with today as the status date, so the numbers move as the CSV changes.

Next deliverable
4 days
Project Proposal, due Sun Sep 20 (5 percent of the grade)
Schedule health
29%
Earned activity-days; the plan says 32% by today. Slightly behind (index 0.92)
Zero float, open now
29
8 more with 1 to 3 days; 0 overdue
Deliverables submitted
0 of 7
45 percent of the course grade
Semester week
4 of 16
Wed Sep 16; 6 of 50 activities done
Earned 29% of planned activity-daysPlan says 32% by today (the mark)

What we are building

Smart Urban Living

A Smart Urban Apartment Package: a configurable set of smart-home technologies and technology-enabled amenities for modern multifamily rentals. A choice-based conjoint among U.S. renters tells a developer which features to install and what monthly premium they carry. The project page has the attributes, the research questions, the market and the decision log.

Monthly premiumAccess and securityClimate controlLightingPackage managementEV charging

The next four weeks

Open activities with a computed early start inside the window. Solid is done, the hatched tint is what remains, a diamond is an official deadline, the red edge marks zero float. Hover any row for the early and late dates; click a row to light up everything it depends on and everything waiting on it.

On the zero-float chain right now

If any of these slip by a day, the deliverable behind them slips by a day. The critical path page shows the whole chain.

ID Phase Activity Owner Early start Must finish Float Status
P05 Proposal Proposal workshop meeting with the professor (remote, week 4) Team Wed Sep 16 (today) Fri Sep 18 0 d Not started
P06 Proposal Revise to v2: remove AI paste artifacts, fix cross-ref and heading levels, add references, benchmark real competitors with prices, quantify the retrofit market, rework price levels, argue the fit Team Wed Sep 16 (today) Fri Sep 18 0 d In progress
P07 Proposal Move the proposal into the official repo (1-proposal/proposal.qmd, image in images/), apply the workshop feedback, render, spell-check Submitter Sat Sep 19 (in 3 days) Sat Sep 19 0 d Not started
P08 Proposal Final read-through by a second member, commit and push the proposal Submitter Sun Sep 20 (in 4 days) Sun Sep 20 0 d Not started
SP01 Survey plan Lock the attribute list and levels after the workshop: units, price levels with a base-rent anchor, one-line level definitions Team Mon Sep 21 (in 5 days) Wed Sep 23 0 d Not started
SP03 Survey plan Choice question text, the attributes-and-levels table with units, and the design parameters (alternatives per question, questions per respondent, no-choice option) Team Thu Sep 24 (in 8 days) Sat Sep 26 0 d Not started
SP04 Survey plan Survey content as exact text: welcome, consent (18 plus, 'I have read and understand'), education per attribute, respondent info, other questions Team Sun Sep 27 (in 11 days) Mon Sep 28 0 d Not started
SP05 Survey plan Assemble survey_plan.qmd, render, spell-check, commit and push Submitter Tue Sep 29 (in 13 days) Tue Sep 29 0 d Not started

Deliverable chain

Each box is an official deadline. The label on the arrow is the smallest float left in the work feeding that deadline; red means none.

Due next

Every dated item in the next stretch, from the course calendar. Project deliverables are the ones this site exists for; homework and quizzes are shown because they compete for the same weeks.

When Kind Item Where State
Wed Sep 16 (today) class Week 4: no lecture, Project Proposal Workshop (remote team meetings with the professor) Remote (scheduling link) In progress
Fri Sep 18 (in 2 days) homework HW3: Quarto and Plotting madd-[netID] repo, hw3/ Upcoming
Sun Sep 20 (in 4 days) project Project Proposal Official team repo, 1-proposal/ In progress
Wed Sep 23 (in 7 days) quiz Quiz 2 (week 3) In class Upcoming
Wed Sep 23 (in 7 days) class Class 5: Quarto and Plotting; project scope (attribute levels, target population, competitors) Tompkins 201 Upcoming
Mon Sep 28 (in 12 days) homework HW4: Intro to surveydown madd-[netID] repo, hw4/ Upcoming
Tue Sep 29 (in 13 days) project Survey Plan Official team repo, 2-survey-plan/ Upcoming
Wed Sep 30 (in 14 days) class Class 6: Intro to surveydown; make the survey plan Tompkins 201 Upcoming

This week

Week 4 (Wed Sep 16): No lecture: Proposal Workshop, remote team meetings with the professor. Project focus: Rubric review of the draft, workshop feedback, revise, move into the official repo, submit by Sun Sep 20. Progress note: Sep 16: brainstorming repo live, official repo joined, draft reviewed against the rubric, tracker replanned with a computed critical path.

See the project page for what we are studying and the decisions so far, the full schedule, the activity list, the requirements coverage, the risk register, the week-by-week table, and the dev log.

EMSE 6035 team project tracker. Public site: no grades, no personal details, no credentials.

 

Built with Quarto and R; the schedule is computed from data/*.csv on every render.